Sports wood floor installation method
When the sports wood floor is installed, the effect is not very satisfactory because of some details, which will have a certain impact on the service life of the sports wood floor. Therefore, the preliminary preparation and installation of the sports wood floor installation are particularly important.
Preparation of sports wood flooring before installation
In the installation of sports wood flooring, it is necessary to do a good job of preparatory work and not be able to enter the site for temporary installation, so it will affect the arrangements of employees. Before the installation of sports wood flooring installation, the following projects must be completed:
1. The foundation in the hall is completed and the maintenance period is not less than 28 days.
2. Decoration and decoration works in the hall must be completed and related personnel must be removed.
3. Installation and commissioning of the lighting and lighting project in the hall.
4, the museum audio installation and debugging.
5. Installation and adjustment of acoustic engineering in the hall.
6, ventilation and installation of air conditioning in the museum.
7. Installation and debugging of display and related timing and scoring equipment in the hall.
8, the roof of the museum waterproof, leakproof must pass the acceptance.
9. Installation, commissioning and acceptance of fire facilities in the hall.
10. Anti-termite treatment in the hall (especially for sports wood floor pits to prevent termites).
11, the museum equipment embedded project.
12. The installation of strong electricity and weak electricity in the hall was completed.